sherbino-ii-substation-and-interconnect
- Facts and Figures
-
138 KV
- Delivery Method
- Engineer, Procure and Construct
138 KV
The Sherbino II 138 kV Substation & Interconnect were completed in September 2012, in Pecos County, Texas. The EPC Project scope included civil work, foundations, erection of steel structures, wiring, and terminations. The project is located on a mesa that spans almost 10,000 acres and rises 3,000 feet above sea level with rocky terrain and is nearly two hours away from the nearest major city. Construction in less than four months under an EPC contract with BP Wind Energy